Weert Malt Tower

We were commissioned to assemble scaffolding around the tower in Weert. This tower is the face of Weert and will be completely renovated.
The assembly of the scaffolding was completed in 6 working days.

The duration of the project will be 25 weeks.

DAW Service took care of the complete project here.